Contractor and Subcontractor Payment Recovery at a Glance
| Question | Short answer |
|---|---|
| Which law governs construction payment disputes? | The contract first, then the muqawala (contract for work) provisions of the civil law. Since 1 June 2026, that is the Civil Transactions Law (Federal Decree-Law No. 25 of 2025) |
| Can a contractor stop work if not paid? | Possibly, under the contract and the civil law’s suspension rules, but wrongful suspension is risky. Follow the notice steps |
| Can a contractor keep the property until paid? | A right of retention may exist where the work has produced a beneficial effect, subject to the facts |
| Can a subcontractor claim directly from the employer? | Only narrowly. Commentary says the subcontractor’s direct claim is limited, and sources differ on the exact test |
| Is retention money a legal requirement? | No. Retention is a contractual mechanism, commonly 10% of each interim payment |
| What routes recover the money? | Negotiation, a payment order, cheque execution, precautionary attachment, a lawsuit or arbitration |
| What decides the case? | Certificates, variation approvals, notices, delivery and progress records |
Why Construction Payments Go Wrong
Most disputes follow a familiar pattern.
- Interim certificate delays. The engineer or consultant is slow to certify, or certifies less than the contractor claimed.
- Variations without paperwork. Extra work is done on verbal instructions, and the price is never agreed in writing.
- Retention held too long. Release dates are missed, or defects are used as a reason to hold the money.
- Set-off and deductions. The employer deducts delay damages or defect costs, and the contractor disputes the amounts.
- Pay-when-paid clauses. The main contractor says it cannot pay until the employer pays.
- Cash-flow chain failure. One party fails, and unpaid sums roll down the chain to subcontractors and suppliers.
- Bounced cheques. Payment cheques are returned, which is both evidence of the debt and an enforcement route.
Understanding where your claim sits in this pattern helps you choose the right remedy.
The Legal Framework
Construction work contracts in the UAE are muqawala contracts. Under the 1985 Civil Code they were governed by Articles 872 to 896. Under the Civil Transactions Law, which took effect on 1 June 2026 and repealed the 1985 Civil Code, commentary says the corresponding provisions are Articles 812 to 839. The new law restates the muqawala rules, adds clearer notice obligations and judicial powers, and strengthens the contractor’s entitlement to interim payments commensurate with completed work.
In practice, the contract usually does most of the work. Many projects use FIDIC-style forms or bespoke contracts, with detailed provisions on payment applications, certification periods, variations, retention, suspension and dispute resolution. Courts and arbitrators read the civil law together with the contract, so start with the contract’s own payment and notice clauses.
For the effect of the new law on contracts more generally, see our guide to the Civil Transactions Law and creditors.
Remedies for a Main Contractor Against the Employer
1. Formal notice and negotiation
Start with a written demand that identifies the certificate or invoice, the amount, the contract clause and the deadline. Where the contract has notice requirements, follow them exactly. A notice that misses a contractual step can be attacked later. See our guide to a legal notice for payment in the UAE.
2. Suspension of work
When an employer does not pay a certified interim payment, commentary says a contractor may be able to suspend work, under the contract and under the civil law’s rules on reciprocal obligations. The new law is described as introducing a statutory right to suspend where payment is withheld without justification.
Be careful. Suspending without following the required notices, or where the employer has a genuine defence, can expose the contractor to claims for delay. Take advice before you stop work.
3. Right of retention
Both the old and new frameworks are described as allowing a contractor to hold property on which its work has produced a beneficial effect until the agreed price is paid. How this works depends on the type of work and the contract, so it is not a universal remedy.
4. Payment order
Where the debt is fixed, due and proven in writing, such as by a signed certificate, a signed statement of account or a written acknowledgement, a payment order can be a fast route. See our guide to the payment order in the UAE. It is unlikely to work where the employer genuinely disputes quality, delay or the amount.
5. Cheque execution
If the employer or main contractor paid with a cheque that was returned, you may be able to use the cheque rules. See our guides to the bounced cheque law in the UAE and the security cheque in the UAE.
6. Precautionary attachment
If there is a real risk that assets will be moved, a contractor can ask the court for precautionary measures. See our guide to bank account attachment and asset seizure in the UAE.
7. Lawsuit or arbitration
Disputed claims, large variation accounts and delay and defect counterclaims usually need a full process. Check the contract’s dispute clause, which may require arbitration, a dispute board or a tiered process before litigation. If the employer is a free zone company, check the forum as well. See our guide to free zone debt recovery in the UAE.
Remedies for a Subcontractor
A subcontractor’s main claim is against the party it contracted with, normally the main contractor.
- Contractual claim. The subcontract sets the price, the payment terms and the notice steps. Most claims stand or fall on these.
- Direct claim against the employer. This is the area where sources differ. One current overview says a subcontractor has no direct claim against the employer unless the main contractor has formally assigned that right. Another commentary on the new law says the direct claim is limited to amounts where the main contractor has referred the subcontractor to the employer, and that mere knowledge or benefit is not enough. The safe approach is not to assume you have a direct claim. Ask a lawyer before you rely on one, and put any direct payment arrangement in writing.
- Pay-when-paid and pay-if-paid clauses. A main contractor may argue that it need not pay until the employer pays. The wording, the facts and the law decide whether this works, so review the clause with a lawyer.
- Suspension and retention. The same cautions apply as for main contractors.
Retention Money
Retention is a percentage withheld from each interim payment as security for defects. Commentary on UAE practice describes 10% as common, often released in two parts: at taking over and at the end of the defects notification period. There is no general statutory requirement for retention, and retention money is generally not required to be held in a separate account, so everything depends on the contract.
The most common retention problems are missed release dates and defect claims used to hold the money. Diary the release dates and send a formal release request at each milestone.
Variations: The Biggest Source of Disputes
Unpaid variations are recoverable if you can prove the instruction, the scope, the price basis, the approval or acceptance, and the amount. The usual weaknesses are verbal instructions, unclear scope and missing price agreements. Get written confirmation before you do extra work, and keep a variation register.
Evidence That Wins Construction Payment Claims
- The contract and all amendments, including any subcontract and side letters.
- Payment applications and interim payment certificates, with the consultant’s comments and any rejection notes.
- Variation orders, site instructions and approvals.
- Measurement and progress records, photos, daily reports and site meeting minutes.
- Delivery notes and material receipts.
- Notices and correspondence, including proof of delivery.
- A statement of account that separates certified, disputed and retention amounts.
- Returned cheques and bank memos, if any.
- Any written acknowledgement of the debt by the employer or main contractor.
Do not put every unpaid amount into one number. A single mixed claim lets the other side attack the weakest item and delay the rest. Separate certified sums, approved variations, retention and disputed items.
Step-by-Step Recovery Plan
- Review the contract’s payment, notice and dispute clauses.
- Build the evidence file and a clean statement of account.
- Send the formal notice exactly as the contract requires.
- Negotiate, and if a payment plan is agreed, put it in writing with security. See our guide to a debt settlement agreement in the UAE.
- Choose the court or arbitration route based on the documents, the dispute and the forum clause.
- Consider precautionary measures if the debtor is at risk of moving assets.
- Enforce the result through the Execution Court, including attachment and, where available, a travel ban. See our guide to the travel ban for debt in the UAE.
- Watch your deadlines. See our guide to the debt limitation period in the UAE.
For Employers and Main Contractors Who Are Being Chased
If you are the party being asked to pay, take the claim seriously.
- Respond to notices on time, and state your objections clearly with evidence.
- Pay the undisputed part and dispute the rest, rather than withholding everything.
- Record deductions properly, such as delay damages and defect costs, in line with the contract.
- Do not rely on pay-when-paid wording without checking that it applies.
- Negotiate a documented plan if you need time.
- Do not leave cheques you cannot cover. A returned cheque creates enforcement risk.
Illustrative Scenarios
These are simplified examples, not real cases.
Scenario 1: The certified but unpaid invoice. A main contractor holds a signed interim payment certificate that the employer has not paid. It serves a formal notice, then uses the certificate and a signed statement of account to apply for a payment order.
Scenario 2: The unrecorded variation. A subcontractor builds extra work on the main contractor’s verbal instruction. When payment is refused, it has no written approval and must rely on messages and site records, which makes the claim harder.
Scenario 3: The pay-when-paid defence. A main contractor refuses to pay a subcontractor because the employer has not paid. The subcontractor reviews the clause, finds the wording is unclear, and negotiates a partial payment while the legal position is assessed.
Common Mistakes Contractors and Subcontractors Make
- Doing variations without written approval.
- Missing contractual notice steps.
- Suspending work without checking the rules.
- Assuming a direct claim against the employer.
- Mixing certified, disputed and retention amounts into one claim.
- Losing track of retention release dates.
- Ignoring the dispute resolution clause, such as arbitration or a dispute board.
- Waiting too long, while deadlines run and the debtor’s position worsens.
How Dubai Debt Recovery Can Help
We review your contract, certificates and variation records, build a clean claim, and send formal demands. We negotiate payment plans and settlements that are written and secured, coordinate with licensed lawyers for payment orders, cheque execution, litigation or arbitration, and support enforcement and skip tracing where a debtor goes quiet.
Our model is No Win, No Fee for collection, with the fee structure confirmed in writing before we start. Court fees, arbitration costs, translation costs and lawyer fees may be separate. Legal opinions, court filings and representation are provided only by licensed lawyers or legal consultants, who may be our partnered legal associates.
Start your free case review or call +971-50-5071820.
Related reading: UAE Debt Collection Laws | What to do if the debtor disputes a debt | How is debt settled in the UAE? | Ways to avoid bad debt | Debt collection Abu Dhabi
Disclaimer: This article is general information, not legal advice. Construction payment rights depend on the contract, the facts and the law that applies, and the civil law changed on 1 June 2026. Legal opinions, court filings, arbitration submissions and representation are provided only by licensed lawyers or legal consultants. Have a licensed UAE lawyer review your contract and claim before acting.